This project commenced initially with the installation of crew vanity units and USB sockets, which was carried out in service over a 3 month period.
In December 2019 our team boarded the vessel for a 12 day Out Fitting Project. The crew area was completely stripped and rebuilt to provide a fully both a fully emersive social space and a relaxing area for crew members.
- Complete upgrade of crew mess, crew bar, wardroom, and officers mess – all new floor coverings, ceilings, wallcoverings; fixed furniture and loose furniture, catering equipment, lighting, and electrical upgrades – ‘The Hub’ design.
- Crew Toilets – Complete upgrade, new floor tiles, wallcoverings, vanity units, mirrors.